Invoice Archive
Contract Number
&
Estimate Numbers are listed below
Please note:
All estimates are listed. Credit invoices are not processed
for payment, however, they are provided for access to pay items which
may be new or reduced work in place for the estimate.
Archive 76F09 / 00
|
State of Illinois
Department of Transportation
Current Report
| DOT Vendor: |
C59420 |
|
Contract: |
76F09 |
| Route: |
FAI 55 FAI 70 |
|
From Date: |
02/27/2012 |
| Section: |
82-3HVB-HDF |
To Date: |
11/13/2012
|
| Project: |
|
State Job: |
C-98-076-11 |
| Letting Date: |
01/20/2012 |
|
Dist/Cnty: |
08 - 163
(ST. CLAIR ) |
|
|
|
|
|
|
Payee: |
THOMAS INDUSTRIAL COATINGS INC
|
|
|
|
|
2070 HIGHWAY Z
|
|
|
|
|
PEVELY , MO 63070
|
|
|
| Percent Completed: 89.85% |
Contract Awarded
Amount |
Additions |
Deductions |
Total Adjusted
Contract Value |
Total Amount
Due to Date |
| 96,460.00 |
0.00 |
0.00 |
96,460.00 |
86,665.00 |
|
Total retainage incld this est held by IDOT:
|
|
|
0.00 |
| Total due after retainage: |
|
|
86,665.00 |
| Mobilzation Paid: | | | 870.00 |
| Total
paid this estimate: |
|
|
86,665.00 |
|
Previous payments to contractor: |
|
|
-4,335.00 |
|
Payment to contractor this estimate: |
|
| 82,330.00 |
| |
|
Voucher # DH28531 | Date: 11/15/2012 |
|
1
of 1
|
82,330.00 |
|
---------------------------------------------------------------------------------------------------------------------------------------------- |
|
Includes 15% mobilization |
|
Pay Estimate Number: 01 |
Total: |
82,330.00 |
Report of Resident Engineer
Completed Work-In Place
For This Estimate Only
|
|
|
PAY ITEM |
QUANTITY |
PAYMENT |
|
Number |
Description |
Awarded |
Net of Adds/
Deducts |
Total Adjusted |
Completed Prior Est. |
Completed to Date |
This Estimate |
$ Unit Price |
$ This Estimate |
| X5060601 |
C&D N-LEAD PT C RS N1 |
1.000 |
0.000 |
1.000 |
0.000 |
1.000 |
1.000 |
3,800.00 |
3,800.00 |
| X5060602 |
C&D N-LEAD PT C RS N2 |
1.000 |
0.000 |
1.000 |
0.000 |
1.000 |
1.000 |
2,640.00 |
2,640.00 |
| 50606701 |
C & P STRUCT STL L1 |
1.000 |
0.000 |
1.000 |
0.000 |
1.000 |
1.000 |
33,850.00 |
33,850.00 |
| 50606702 |
C & P STRUCT STL L2 |
1.000 |
0.000 |
1.000 |
0.000 |
1.000 |
1.000 |
24,510.00 |
24,510.00 |
| 59200101 |
BRIDGE WASHING N1 |
1.000 |
0.000 |
1.000 |
0.000 |
1.000 |
1.000 |
8,330.00 |
8,330.00 |
| 59200102 |
BRIDGE WASHING N2 |
1.000 |
0.000 |
1.000 |
0.000 |
1.000 |
1.000 |
8,330.00 |
8,330.00 |
| 67100100 |
MOBILIZATION |
1.000 |
0.000 |
1.000 |
0.289 |
0.347 |
0.058 |
15,000.00 |
870.00 |
|
Total: |
$82,330.00 |
|
Return to the IDOT Home Page
|