SPRINGFIELD, IL -- The Illinois Department of Transportation will
open bids on March 7, 2003 for various road and bridge improvement
projects located throughout the state. Also included are 24
aeronautics projects and one land reclamation project.
Following is a list of the projects by county:
1. Adams County, US 24, District 6, Contract No. 72753, 2 miles
of pavement patching, bituminous concrete resurfacing and 3 ft width
aggregate shoulders on US 24 between Clayton and IL 94. 25 Working
Days.
2. Cook County, IL 394, District 1, Contract No. 62422, 3.64
miles of milling and bituminous concrete surface on IL 394 from
Thornton-Lansing Road to Joe Orr Road in Lansing, Glenwood and
Lynwood. Completion Date August 28, 2003 Plus 10 Working Days.
3. DuPage County, IL 59, District 1, Contract No. 62294, 1.42
miles of milling and bituminous concrete surface on IL 59 from
Glacier Park to McCoy Drive in Aurora and Naperville. Completion
Date July 18, 2003 Plus 05 Working Days.
4. Fayette County, I-70, District 7, Contract No. 94906, 3.21
miles of pavement patching, bituminous surface removal, bituminous
concrete resurfacing, 6 ft and 10 ft width bituminous shoulders and
2 ft width aggregate shoulders on I-70 east of Vandalia from the
Kaskaskia River bridge east to 1 mile west of US 40. 80 Working
Days.
4P. Madison County, IL 255 (Alton Bypass), District 8, Contract
No. 76384, 7.05 kilometers of grading and variable width paving, 1.8
m and 3 m width bituminous shoulders, five concrete box culverts,
and three concrete noise barrier walls on IL 255 (Alton Bypass) from
IL 143 to IL 140. Completion Date July 31, 2004.
5. Hancock County, IL 94, District 6, Contract No. 72417,
pavement patching, bituminous surface removal, bituminous concrete
resurfacing and 3 ft width aggregate wedge shoulders on IL 94 from
Powellton Road south 4.02 miles to just northeast of Ferris. 35
Working Days.
6. McHenry County, IL 120, District 1, Contract No. 62226, 2.14
miles of milling and bituminous concrete surface on IL 120 from US
14 to Throop St. in Woodstock. 30 Working Days.
6P. Madison County, IL 159, District 8, Contract No. 76014, The
widening and resurfacing to five lanes 3.64 km of IL 159 from north
of I-270 to Harvard Drive in Edwardsville, the construction of 728 m
of relocated IL 159, the reconstruction of Kettle River Drive and
Cougar Road, the widening and resurfacing of Center Grove Road to
add through and right turn lanes and the extension of pedestrian box
culvert, all located in Glen Carbon and Edwardsville. Completion
Date June 15, 2004.
7. Montgomery County, I-55 East Frontage Road, District 6,
Contract No. 72752, 2 miles of pavement patching, bituminous
concrete resurfacing and 3 ft width aggregate shoulders on the I-55
East Frontage Road between Litchfield and IL 108. 25 Working Days.
8. Montgomery County, I-55 West Frontage Road, District 6,
Contract No. 72756, 2 miles of pavement patching, bituminous
concrete binder and surface courses and 6 ft width aggregate
shoulders on the I-55 West Frontage Road north of Farmersville. 25
Working Days.
9. Pike County, IL 100, District 6, Contract No. 72146, 5.96
miles of pavement patching, bituminous surface removal, bituminous
concrete resurfacing, 5 ft and 3 ft width bituminous shoulders, 3 ft
width aggregate shoulders, guardrail removal and installation on IL
100 between Milton and Pearl. Completion Date November 30, 2003.
10. Pike County, IL 106, District 6, Contract No. 72761, 2.40
miles of pavement patching, bituminous surface removal, bituminous
concrete resurfacing and 3 ft width aggregate shoulders on IL 106
west of Pittsfield beginning near US 54 and extending northwest. 25
Working Days.
11. Williamson County, IL 148, District 9, Contract No. 98778,
West of Marion at the intersection of IL 148 and Old IL 13/West Main
Street the southbound left turn lane will be reconstructed and a
northbound left turn lane will be added to IL 148. On West Main
Street a left turn lane and a right turn lane will be added and new
traffic signals will be installed at the intersection. Completion
Date August 29, 2003 Plus 08 Working Days.
12. Williamson County, IL 13, District 9, Contract No. 98757, IL
13 in Marion at the intersection with North Carbon Street, the work
will consist of pavement removal, PCC pavement, a bituminous inlay,
detector loops and the modification of an existing controller
cabinet. Also, included is work on eastbound IL 13 between Russell
Street and Bentley Street and on westbound IL 13 between Russell
Street and the EN Baker entrance consisting of bituminous shoulder
installation. Completion date July 31, 2003.
12P. Madison County, IL 159, District 8, Contract No. 76013, 1.82
kilometers of widening to five lanes and resurfacing of IL 159 from
IL 162 in Maryville to Glen Crossing Road in Glen Carbon. Completion
Date November 01, 2004.
13. Cook County, IL 7, District 1, Contract No. 62535, Deck beam
support system for the structure carrying IL 7/Southwest Highway
over B & OCT Railroad, Melvina Ditch and Stony Creek in Chicago
Ridge. 15 Working Days.
14. Cook County, US 20 (Lake Street), District 1, Contract No.
62092, Removal and replacement of the superstructure of the US
20-Lake St. bridge over IL 64 (North Ave); reconstruction of the
intersection of US 20 and Railroad Ave. and retaining wall
construction, lighting and traffic signal installation all in
Northlake, Addison, Leyden, York and Proviso. Completion Date
October 31, 2003 Plus 05 Working Days.
15. Jackson County, IL 4, District 9, Contract No. 98609, The
removal of the existing 3 span bridge carrying IL 4 over Rattlesnake
Creek southwest of Vergennes and replacement with a 3 span,
continuous composite concrete and steel beam. 110 Working Days.
15P. Madison County, IL 255, District 8, Contract No. 76527,
reconstruction of Wood Station Road on new vertical and horizontal
alignments and the construction of a 2 span, continuous composite
concrete and steel web plate girder structure on vaulted abutments
to carry Wood Station Road over proposed IL 255 northeast of Alton.
Completion Date July 01, 2004.
16. Madison County, I-55/70, District 8, Contract No. 76620, 50
feet of bridge repair on the eastbound I-55/70 bridge over Wilson
Avenue south of Maryville consisting of beam replacement and
superstructure removal and replacement. 15 Working Days.
16P. Peoria County, I-74, District 4, Contract No. 68193,
Reconstruction of the arterial roadway system on Sterling Avenue,
thru University Street including widening on Interstate 74 from
University Avenue to 0.4 km west of the Union Pacific Railroad and
the removal and the reconstruction of the Gale, University,
Broadway, Sheridan and Ellis structures over I-74 in Peoria.
Completion Date November 19, 2004.
17. Stark County, IL 17, District 4, Contract No. 88802, Removal
and replacement of the structure carrying IL 17 over Camp Run Creek
Tributary located 3.8 miles east of Wyoming. 35 Working Days.
17P. Peoria County, I-74, District 4, Contract No. 68194,
Reconstruction of the arterial roadways system in the downtown area
of Peoria between Armstrong Avenue and Adams Street, including the
construction of the Armstrong Avenue interchange from Ellis Street
on Interstate 74 east to Columbia Terrace in Peoria. Completion Date
November 19, 2004.
18. Wayne County, IL 15, District 7, Contract No. 94914, removal
of the bituminous wearing surfaces and waterproofing membrane
systems, partial and full depth deck patching, keyway repair, formed
concrete repairs, new expansion joints, concrete wearing surfaces
and new guardrail at 4 structures on IL 15 at the following
locations east of Fairfield: (1) over Pond Creek 1.5 miles east of
Fairfield (2) over an unnamed stream 4 miles west of the Edwards
County Line (3) over Whiteoak Overflow 1.5 miles west of the Edwards
County line and (4) over an unnamed stream 0.9 mile west of the
Edwards County line. 90 Working Days.
18P. Tazewell County, I-74, District 4, Contract No. 68195,
Reconstruction of the Eastbound and Westbound lanes of I-74 and
ramps, structures, earthwork, lighting, signing and retaining walls
located at the I-74/Riverfront Drive interchange in East Peoria,
immediately southeast of Murray Baker Bridge. Completion Date
October 01, 2005 Plus 20 Working Days.
19. Cook County, IL 43, District 1, Contract No. 62209, Traffic
signal modernization on IL 43 from 32nd St. to 34th St. in
Riverside. 35 Working Days.
20. Madison-St. Clair Counties, IL 162 & IL 203, District 8,
Contract No. 76643, Modernization of traffic signals at the
following intersections:(1) IL 162 and IL 203 (Nameoki Road) at
Granite City (2) IL 203 and 20th Street at Granite City (3) IL 162
at Mockingbird Lane and CH 35 (Horseshoe Lake Road) at Granite City
(4) IL 203 and Ohio Avenue/Landfill/Raceway at Madison and (5) IL
203 at Big Bend Road/Eagle Park Road at Madison. 25 Working Days.
21. Cook County, State Street, District 1, Contract No. 62453,
Concrete pavement patching on State Street from south of Sauk Trail
to north of Steger Road in South Chicago Heights and Steger. 20
Working Days.
22. Cook County, Various routes, District 1, Contract No. 62462,
Bridge parapet repair and fence repair for bridges at various
locations. 45 Working Days.
23. DuPage/Will Counties, I-55 & I-80, District 1, Contract No.
62482, Bridge painting at 1 location on I-55 and 3 locations on I-80
in DuPage and Will Counties. 50 Working Days.
24. Madison County, IL 255, District 8, Contract No. 76630, The
work will consist of planting and caring for 20,900 seedlings as
part of the tree mitigation on 49 acres along the west side of IL
255 between the Wagon Wheel Road and the Cahokia Diversion Channel
and east of the Union Pacific Railroad at Roxana. 15 Working Days.
25. Madison County, Horseshoe Lake Rd (CH 35), District 8,
Contract No. 76511, The removal of the three corrugated metal pipe
culverts on Horseshoe Lake Road 0.30 mile west of IL 111 at Pontoon
Beach and replacement with a 10' X 8' precast concrete box culvert.
20 Working Days.
26. Saline County, IL 13, District 9, Contract No. 98779,
Demolition of 26 state acquired buildings for the relocation of IL
13 through Harrisburg. 30 Working Days.
27. St. Clair County, IL 15, District 8, Contract No. 76628,
removal of the existing guardrail turn-down terminals in the median
of east leg of the intersection of IL 15 and the entrance to Our
Lady of the Snow Shrine in Belleville and the replacement with a
traffic barrier terminal. Completion Date May 31, 2003.
28. St. Clair County, Various Routes, District 8, Contract No.
76631, Crack routing and sealing at the following locations in St.
Clair County: (1) 2.6 miles on Salem Place from IL 159 to Old US 50
at Fairview Heights and O'Fallon (2) 0.40 mile on Boul Avenue from
Morgan Street to IL 159 at Swansea (3) 1 mile on IL 158 from IL 161
to IL 177 southeast of Shiloh (4) 1.15 miles on US 50 from just west
of Old US 50 to just east of Old US 50 at Summerfield (5) 4.5 miles
on IL 161 from Old IL 158 to east of IL 4 north of Mascoutah (6) 3.0
miles on Old US 50 from US 50 to the Clinton County Line east of
Summerfield (7) 1.65 miles on Foley Drive from Millie Street to Main
Street at Belleville and (8) 0.60 mile on Shiloh Valley Township
Line Road northeast of Shiloh. Completion Date June 20, 2003.
29. Lake County, Various routes, District 1, Contract No. 44810,
Applying assorted types and widths of paint pavement markings at
various locations. Completion Date November 01, 2003.
30. Various County, Various routes, District 1, Contract No.
44808, Removal of assorted types, widths and sizes of pavement
markings at various locations. Completion Date June 30, 2004.
31. Various County, Various routes, District 1, Contract No.
44809, Installing raised reflective pavement markers at various
locations. Completion Date November 01, 2003.
32. Various County, Various routes, Districts 8 & 9, Contract No.
44807, repairing various widths of thermoplastic preformed plastic,
epoxy, hot spray thermoplastic and polyurea pavement marking lines,
letters and symbols and the removal of existing pavement markings on
various routes throughout Districts 8 & 9. Completion Date June 30,
2004.
33. Will County, I-80, District 1, Contract No. 62486, Cleaning
and painting of bridges along I-80 at four locations from IL 53 to
Richard Street in Joliet. 50 Working Days.
34. Will County, I-57, District 1, Contract No. 62492, Peotone
Weigh Station repairs located 3.6 miles north of Peotone (I-57 NB)
and 3.9 miles north of Peotone (I-57 SB). 20 Working Days.
35. Ogle-Winnebago Counties, I-39, District 2, Contract No.
64797, Reconstruction of the existing slopes in three areas,
reestablishing existing ditch flow lines and maintenance of existing
drainage structures on Interstate 39 from the Lee/Ogle County line
to 1.53 miles north of the Winnebago line. 55 Working Days.
36. Clay County, CH 4, District 7, Contract No. 95353,
reconstructing the existing roadway with an 8" soil cement base
course, from Jasper County Line to FAS Route 799. 30 Working Days.
37. Cook County, Busse Rd / Landmeier Rd, District 1, Contract
No. 83609, 0.60 miles of widening and resurfacing, curb and gutter,
medians, sidewalks, traffic signals, landscaping and pavement
markings at the intersection of IL 83 and Landmeier Rd in Elk Grove.
Completion Date November 14, 2003.
38. Cook County, Washington Avenue, District 1, Contract No.
83673, 2,106 feet of reconstruction, widening and resurfacing,
drainage, water main, pavement marking and landscaping on Washington
Avenue from Maple Avenue to Prairie Avenue and Veteran's Circle in
Brookfield. Completion Date August 15, 2003.
39. DeWitt County, US 51 BUS 51, District 5, Contract No. 90792,
3.45 miles of bituminous concrete resurfacing, storm sewer upgrade,
geometric and safety improvements along BUS 51 Bypass (N) to U.S. 51
Bypass (S) in Clinton. Completion Date September 13, 2003.
40. DuPage County, Unmarked Route, District 1, Contract No. 83674
grinding and resurfacing with level binder, area reflective crack
control, and bituminous surface course of 2.2 miles on Main Street
and Fairview Avenue in Downers Grove. 45 Working Days.
41. Edwards County, CH 1, District 7, Contract No. 95345,
repairing the existing base and 2.46 miles of bituminous
resurfacing, aggregate shoulders and related services on County
Highway 1 from Bone Gap north. 15 Working Days.
42. Kankakee County, IL 113, District 3, Contract No. 66248, 8.3
miles of milling and resurfacing on IL 113 from north of Tower Road
near Kankakee to the Will County line. Completion Date July 01,
2003.
43. Moultrie County, CH 4, District 5, Contract No. 91273,
rubblizing approximately 1.23 miles of existing non-reinforced PCC
pavement and resurfacing the entire length with 6" thickness
bituminous concrete pavement, providing aggregate shoulders and pipe
underdrains on both sides, as well as other work incidental to
completing these improvements to Bruce-Findlay Road, approximately
2.5 miles east of the Shelby County Line in Moultrie County. 50
Working Days.
44. Peoria County, IL 116, District 4, Contract No. 68296, 1.32
miles of bituminous concrete resurfacing on IL 116 from Griswald
Street to Adams Street in Peoria. 25 Working Days.
45. Richland County, CH 9, District 7, Contract No. 95344,
Reconstructing the existing surface with an 8" soil cement base
course on CH 9 beginning at Pureton extending northerly for 8.96
miles. 30 Working Days.
46. Rock Island County, 23rd Avenue, District 2, Contract No.
85257, 0.139 mile replacement of pavement, curb and gutter,
sidewalks and signals on 23rd Avenue from 24th Street to 27th Street
in Moline. 90 Working Days.
47. St. Clair County, I-55/70, District 8, Contract No. 76550,
0.10 miles of construction of a free flowing 18 ft width turnaround
road between Main Street and Fourth Street in East St. Louis for
detoured traffic from the Poplar Street Complex. Completion Date
July 07, 2003 Plus 20 Working Days.
48. Vermilion County, Henning Road, District 5, Contract No.
90335, 10.75 miles of bituminous concrete resurfacing on Henning
Road from US 136 to Hungry Hollow Road northwest of Danville.
Completion Date August 15, 2003 Plus 05 Working Days.
49. Vermilion County, IL 49, District 5, Contract No. 90911,
14.19 miles of bituminous concrete resurfacing on IL 49 from US
136(W) to US 150 west of Fithian. 65 Working Days.
50. Whiteside County, Lynn Boulevard, District 2, Contract No.
85307, 0.474 mile of earth excavation, aggregate base course with
aggregate shoulders, pipe culverts and other related appurtenances.
30 Working Days.
51. Christian County, CH 8, District 6, Contract No. 93336,
Construction of a two span, precast, prestressed concrete deck beam
bridge and approaches carrying CH 8 over Locust Creek, 2.0 miles
west of Owaneco. 55 Working Days.
52. Cook County, Wood Street, District 1, Contract No. 62038,
Removal of the existing structure and replacement with a 3-sided
precast concrete structure carrying Wood Street over Cal-Union
Drainage Ditch in Markham. Completion Date September 30, 2003 Plus
10 Working Days.
53. Macon County, CH 28, District 5, Contract No. 91244,
Construction of a single span, precast prestressed concrete deck
beam bridge carrying CH 28 over a tributary to Sangamon River, 5
miles west of Decatur on Mt. Auburn Blacktop. 35 Working Days.
54. Perry County, Park Road, District 9, Contract No. 99174,
Construction of a single span, precast, prestressed concrete deck
beam bridge carrying TR 71 (Park Road) over Little Beaucoup Creek,
5.4 miles west of Tamaroa. 25 Working Days.
55. Pulaski County, CH 3, District 9, Contract No. 99178,
Construction of a single span precast prestressed concrete deck
bridge over the Cache River and reconstruction of approximately 465
ft of CH 3, 0.2 miles north of IL 169. 35 Working Days.
56. Shelby County, CH 23, District 5, Contract No. 91268,
Construction of a single span, precast, prestressed concrete deck
beam bridge carrying CH 23 over Henry Creek, one mile west of Sigel.
60 Working Days.
57. Tazewell County, US 150, District 4, Contract No. 88801,
Removal / demolition of the structure carrying US 150 over the
abandoned Penn R.R. and replacement with a cast-in-place box culvert
for a future bike path located 0.3 mile west of Veterans Road in
Morton. Completion Date November 30, 2003 Plus 15 Working Days.
58. Tazewell County, US 150/24, District 4, Contract No. 68350,
Replacement of the joints on the McCluggage Bridge (WB only)
carrying IL 150/24 over the Illinois River in East Peoria.
Completion Date June 30, 2003.
59. Cook County, IL 68, District 1, Contract No. 83642,
Intersection and transition lighting will be provided at the
intersections of Dundee Road and Arlington Heights Road and also the
intersection of Dundee Road and Buffalo Grove Road in Buffalo Grove.
85 Working Days.
60. DeKalb County, IL 23, District 2, Contract No. 64806, Traffic
signal modernization and intersection channelization at IL 23 and IL
38 in DeKalb. 15 Working Days.
61. Lake County, IL 83, District 1, Contract No. 60715, Traffic
signal modernization at the intersection of IL 83 at Shorewood Road
in Grayslake. 35 Working Days.
62. Cook County, Various routes, District 1, Contract No. 83675,
1.22 miles of portland cement concrete sidewalk at various locations
on Belle Drive, Country Club Drive, Charles Drive and Hillside
Avenue in Northlake. 40 Working Days.
63. Cook-Will Counties, Various routes, District 1, Contract No.
62497, Crack and joint routing and sealing along various routes in
Cook and Will Counties. 25 Working Days.
64. DuPage County, US 34/Ogden Ave., District 1, Contract No.
83657, 1.81 miles of PCC sidewalk improvements and pedestrian
traffic signals on US 34/Ogden Avenue, from Radcliff Road to Old
Tavern Road, and from River Drive to Ivan Avenue in Lisle. 40
Working Days.
65. Jersey County, Fairgrounds Ave. & June St., District 8,
Contract No. 97206, paving, grading & storm sewers for the extension
of Fairgrounds Avenue and June Street in Jerseyville. 65 Working
Days.
66. Kane County, IL 38, District 1, Contract No. 62499, Crack and
joint routing and sealing along IL 38 from Randall Road to IL 47 in
Elburn and St. Charles. 15 Working Days.
67. Kane County, IL 64, District 1, Contract No. 62500, Crack and
joint routing and sealing along IL 64 from IL 47 to the DeKalb
County line in Virgil and Lily Lake. 15 Working Days.
68. Livingston County, IL 47, District 3, Contract No. 66307,
regrading roadside ditches and collateral drainage improvements
along 1,568 ft of IL 47 just north of the intersection with IL 116
near Saunemin. 15 Working Days.
69. Peoria County, US 24, District 4, Contract No. 68314,
Landscaping consisting of tree and shrub planting to create a
natural sight screen on US 24 east of the I-474 interchange north of
Bartonville. Completion Date October 31, 2005 Plus 10 Working Days.
70. Peoria County, IL 29, District 4, Contract No. 68328,
Demolition of a house located at 1315 N. 4th Street in Chillicothe.
15 Working Days.
71. Peoria-Tazewell Counties, I-74, District 4, Contract No.
68308, Placement of temporary informational signing along various
routes (including detour I-474) for the reconstruction of I-74 in
Peoria and East Peoria. Completion Date November 30, 2006.
72. Pike County, IL 100, District 6, Contract No. 72699, 0.06
mile of the installation of new guardrail, terminals and riprap
along IL 100 west of Pearl. 15 Working Days.
73. Various Counties, Various routes, District 2, Contract No.
64861, Bridge washing at various locations in Henry, Ogle, Putnam,
Rock Island, Whiteside and Winnebago counties. 30 Working Days.
74. Various County, Various, District 7, Contract No. 94950, The
cleaning and painting of 7 bridges carrying various routes over I-70
and US 40 in Effingham and Fayette Counties in District 7. 60
Working Days.
75. Various Counties, Various routes, District 7, Contract No.
94951, cleaning and painting of 11 bridges on various routes in
various counties in District 7. 90 Working Days.
76. Various Counties, I-57, District 5, Contract No. 70311, 48
miles of weed control spraying on Interstate 57 in Coles,
Cumberland, Douglas and Shelby counties. Completion Date October 03,
2003.
77. Will County, Various routes, District 1, Contract No. 62498,
Crack and joint routing and sealing along various routes in Will
County. 15 Working Days.
78. Winnebago County, I-90, District 2, Contract No. 64878,
Routing, cleaning and sealing pavement surface cracks on Interstate
90 from Rockton Road to the Wisconsin State line. 15 Working Days.
79. Champaign County, US 45/Century Blvd. District 5, Contract
No. 70056, 2.19 km of bituminous concrete resurfacing and traffic
signals on US 45/Century Blvd from US 136 to 0.8 miles south in
Rantoul. Completion Date December 01, 2003 Plus 10 Working Days.
80. Gallatin-Saline Counties, IL 13, District 9, Contract No.
98754, 17.58 miles of pavement patching, bituminous surface removal,
bituminous concrete resurfacing, 10 ft and 4 ft width bituminous
shoulders, 6 ft and 2 ft width aggregate shoulders, bridge repairs
and bridge deck microsilica concrete overlays on four bridges on IL
13 between Harrisburg and Old Shawneetown. 115 Working Days.
81. Henry County, US 34, District 2, Contract No. 64507,
Improvement of the intersection at US 34 and Kentville Road by the
addition of an auxiliary lane and left turn lanes, east of Kewanee.
Completion Date August 22, 2003.
82. JoDaviess County, US 20, District 2, Contract No. 64610,
construction of turn lanes at US 20 and Barge Terminal Road east of
East Dubuque. 40 Working Days.
83. Lake County, IL 21, District 1, Contract No. 62442, 2.77
miles of milling and bituminous concrete surface on IL 21 from IL
176 (East Park Avenue) to IL 60 (Townline Road) in Libertyville.
Completion Date October 31, 2003 Plus 05 Working Days.
84. Lake County, Washington Street, District 1, Contract No.
83537, 2.85 km of additional lanes, widening, resurfacing, drainage
system, traffic signals along Washington Street from U.S. 45 to Hunt
Club Road. 215 Working Days.
85. Livingston County, IL 116, District 3, Contract No. 66237,
1.75 miles of bituminous concrete widening and resurfacing of IL 116
from IL 23 to the east city limits of Pontiac. Completion Date
November 30, 2003 Plus 25 Working Days.
86. Madison County, US 67/IL 111, District 8, Contract No. 76099,
1.90 miles of pavement patching, bituminous surface removal,
widening and resurfacing, storm sewers, curb and gutter, and signal
work to provide a bi-directional turn lane and bicycle
accommodations along US 67/IL 111 in Godfrey from Tolle Lane to the
US 267 wye. 95 Working Days.
87. Madison County, IL 255, District 8, Contract No. 76544, 0.89
kilometer of pavement patching, widening and resurfacing,
channelized medians, bituminous & aggregate shoulders, and the
installation of traffic signals on Fosterburg Rd. at the interchange
with IL 255. Completion Date August 31, 2003.
88. McLean County, OR 51, District 3, Contract No. 66316,
bituminous shoulder removal and replacement and guardrail removal
and replacement at 7 culvert locations on OR 51 between Heyworth and
Randolph. 50 Working Days.
89. Sangamon County, Dirksen Parkway, District 6, Contract No.
92822, 4.46 km of reconstruction on Dirksen Parkway between Ridge
Avenue and Peoria Road on the east side of Springfield. Consisting
of pavement patching, widening and resurfacing the existing pavement
to provide two through lanes in each direction and a bi-directional
turn lane, traffic signals, curb and gutter and storm sewers. The
intersections of Sangamon Avenue, Northfield Drive, Atlanta Street,
Walton Drive, Sam's Place and Mayden/Bissel Drive will be
reconstructed. Also, included is the removal of the existing
railroad subway north of the Mayden/Bissel Drive intersection
Completion Date October 31, 2004.
90. Cook County, Torrence Avenue, District 1, Contract No. 62033,
Removal and replacement of the bridge deck and approach slabs,
widening of the pier caps and abutments and lighting on the 9-span
structure carrying Torrence Avenue over Conrail, Baltimore & Ohio,
Chicago Terminal and Indiana Harbor Belt Railroad, in Burnham.
Completion Date September 30, 2003 Plus 10 Working Days.
91. Cook County, Joliet Road, District 1, Contract No. 62117,
Bridge deck replacement and new lighting on the structure carrying
Joliet Road over B&O & IHB Railroad in McCook. Completion Date
October 31, 2003 Plus 10 Working Days.
92. Hancock, IL – Lee, IA Counties, US 136, District 6, Contract
No. 72640, Repairs to the bridge carrying US 136 over the
Mississippi River at Hamilton. Bridge joint repair, relocating the
inspection catwalks underneath the structure, removal and
re-installation of the existing pedestrian handrail to correct loose
anchor studs, and riprap placement at pier 4. Completion Date:
August 1, 2003 Plus 20 Working Days.
93. St. Clair County, Unmarked, District 8, Contract No. 76556,
removal of the 8 span MacArthur Bridge over northbound and
southbound IL 3 near Sauget. 50 Working Days.
94. Wabash County, CH 6, District 7, Contract No. 95355, Removal
of the existing structure carrying CH6 over Fordice Creek 4 miles
north of Bellmont and replacement with an 80 foot long triple span,
precast, prestressed concrete deck beam bridge with earth approaches
and aggregate surface course. 40 Working Days.
95. Livingston County, IL 116, District 3, Contract No. 66312,
Installation of a traffic signal system on IL 116 at WalMart/Norman
Drive and also at Deerfield Road in Pontiac. 45 Working Days.
96. Ford County, I-57, District 3, Contract No. 66292, 0.10 miles
of pavement patching on Interstate 57 at milepost 262, 1.5 miles
north of Paxton. 15 Working Days.
97. Henry County, Unmarked Route, District 2, Contract No. 64483,
Improvement consists of paving the parking lots at Bishop Hill
Historic site west of Kewanee. 15 Working Days.
98. JoDaviess County, US 20, District 2, Contract No. 64876, 10.1
miles of pavement patching on US 20 between East Dubuque and IL 84.
15 Working Days.
99. McLean-Livingston Counties, I-55, District 3, Contract No.
66336, Cleaning and painting 4 structures in McLean and Livingston
counties. 150 Working Days.
100. McLean County, IL 9, District 3, Contract No. 66332, 10.7
miles of crack and joint sealing on IL 9 from the Ford/McLean county
line to Arrowsmith/Colfax Road. 20 Working Days.
101. McLean County, Various, District 3, Contract No. 66329, Weed
control spraying on Interstates 74, 39 and 55 in McLean counties.
Completion Date September 28, 2003.
102. Stephenson County, IL 26, District 2, Contract No. 64893,
Replacement of the topsoil and re-seeding areas along IL 26 near
Fairview Road, north of Freeport. 15 Working Days.
103. Stephenson County, Various routes, District 2, Contract No.
64879, Routing, cleaning and sealing pavement surface cracks on IL
73 from US 20 to the Wisconsin State line, on US 20 BR from US 20
easterly to Freeport, and on US 20 from Freeport to Winnebago
County, a combined distance of 21.36 miles. 15 Working Days.
104. Various Counties, Various routes, District 2, Contract No.
64881, Routing and sealing of cracks on IL 251 from IL 72 to the
Winnebago Ogle county line; IL 251 from IL south to Roosevelt Road;
and on US 20 from Interstate 90 east of Cherry Valley to Interstate
39. 15 Working Days.
105. Various Counties, Various routes, District 2, Contract No.
64863, "On call" guardrail and fence repairs in the north one-half
of District Two on all state maintained routes. Completion Date
March 15, 2004.
106. Various Counties, Various routes, District 2, Contract No.
64862, "On call" guardrail and fence repairs in the south one-half
of District Two on all state maintained routes. Completion Date
March 15, 2004.
107. Various Counties, Various routes, District 2, Contract No.
64883, Applying herbicides along various routes in Bureau, Boone,
Carroll, Henry, Lee, Ogle, Putnam, Rock Island, Stephenson,
Whiteside, Winnebago and JoDaviess counties. Completion Date October
04, 2003.
108. Grundy-LaSalle Counties, Various, District 3, Contract No.
66328, Weed control spraying on Interstate 39,80 and 55 in Grundy
and LaSalle counties. Completion Date May 31, 2003 Working Days.
109. Various County, Various, District 2 & 3, Contract No. 44806,
Repairing various width of thermoplastic, preformed plastic,
preformed thermoplastic, epoxy, hot spray thermoplastic and polyurea
pavement marking lines on various routes in District 2 and 3.
Completion Date June 30, 2004.
110. Various Counties, I-39, District 3, Contract No. 66289,
Patching at 8 interchanges on Interstate 39 from Oglesby Spur in
LaSalle County to US 24 in Woodford County. 35 Working Days.
111. Winnebago County, IL 251, District 2, Contract No. 64877,
0.47 miles of patching on the northbound ramps from IL 251 to
Rockton Road. 15 Working Days.
112. Peoria County, IL 40, District 4, Contract No. 68112, 0.80
mile of bituminous concrete resurfacing on IL 40 from Ravenswood
Road to Lindberg Road in Peoria. Also, bridge repairs to the
structure carrying IL 40 over IL 6. 40 Working Days.
113. Tazewell County, US 150, District 4, Contract No. 68151,
5.06 miles of bituminous concrete resurfacing on US 150 from East
Peoria to east of Detroit Avenue in Morton. Completion Date July 02,
2003.
114. Macoupin County, IL 4 & Old IL 4, District 6, Contract No.
72292, 5.27 km of pavement patching, bituminous surface removal,
bituminous resurfacing, bituminous concrete base course widening,
and aggregate wedge shoulders on IL 4 from the Sangamon County Line
to George Street in Virden; and on Old IL 4 from south of Virden to
IL 4 in Virden. Completion Date September 01, 2003.
115. Clay-Richland Counties, US 50, District 7, Contract No.
94398, 7.43 miles of pavement patching, bituminous surface removal,
bituminous concrete resurfacing, 3 ft width bituminous shoulders and
5 ft width aggregate shoulders on US 50 from west of Clay City to
west of Noble. Also included is the rehabilitation of the bridge
over the Little Wabash River. 90 Working Days.
116. Williamson-Pope Counties, IL 37 & IL 146, District 9,
Contract No. 98762
1.34 miles of pavement patching, bituminous surface removal,
bituminous concrete resurfacing, 1.5 ft width bituminous shoulders
an 2 ft width aggregate shoulders at the following locations: (1)
1.01 miles on IL 37 at Pulleys Mill and (2) 0.33 mile on IL 146 at
Watersburg 30 Working Days.
117. Cook County, Kedzie Avenue, District 1, Contract No. 60914,
0.94 mile of milling and bituminous concrete surface on Kedzie
Avenue from 71st Street to IL 7 and bridge rehabilitation on the
structure carrying Kedzie Avenue over Belt Railway Company Railroad
all in Chicago. Completion Date November 30, 2003 Plus 25 Working
Days.
118. Peoria-Tazewell Counties, I-74, District 4, Contract No.
68226, Supplying an Intelligent Transportation System (ITS) on I-74
from west of Sterling Avenue to east of Washington Street in Peoria
and East Peoria. Completion Date December 31, 2006.
119. Various Counties, Various routes, District 3, Contract No.
66298, Miscellaneous pavement patching at various locations on
various marked routes. Completion Date December 31, 2003.
120. Bond-Madison Counties, I-70 & I-55, District 8, Contract No.
76584, Spot cleaning and painting the structures carrying TR 161
over I-70 at Smithboro; TR 156 over I-70, 7.9 miles east of
Pocahontas; and TR 246 over I-55, 2 miles northeast of Hamel. 65
Working Days.
121. Cumberland-Douglas Counties, Various routes, District 5,
Contract No. 90943, Scour protection at various locations in
Cumberland and Douglas counties. 55 Working Days.
1A. Illinois Valley Regional Airport, Peru, LaSalle County,
Contract No. IL025, Overlay & Mark Existing 6,000' X 100' Runway
18/36 & Taxiways
2A. WITHDRAWN.
3A. U OF I – Willard Airport, Savoy, Champaign County, Contract
No. UN040, Install 8' Class E Animal Control/Security Fence & Gates
4A. Lansing Municipal Airport, Lansing, Illinois, Cook County,
Contract No. LA032, Construct T-Hangar Site Work - Phase 2,
including Grading & Drainage
5A. Peoria Regional Airport, Peoria, Peoria County, Contract No.
PE079, Relocate Runway 31 Glideslope; Relocate RVR; Relocate Runway
31 MALSR System; Relocate Runway 13 Localizer; Remove Runway 31
Middle Marker; Remark Threshold of Runway 13 Localizer
6A. WITHDRAWN
7A. WITHDRAWN,
8A. WITHDRAWN,
9A. WITHDRAWN
10A. WITHDRAWN
11A. WITHDRAWN
12A. WITHDRAWN,
13A. WITHDRAWN
14A. WITHDRAWN,
15A. St. Louis Regional Airport, East Alton, Madison County,
Contract No. SR080, The Reconstruction Of The Aircraft Parking Apron
(Phase IV)
16A. DeKalb-Taylor Municipal Airport, DeKalb, DeKalb County,
Contract No. DK047, Remove & Replace The Airfield Electrical Vault
17A. Lewis University Airport, Romeoville, Will County, Contract
No. LE031, Pave, Light & Mark Runway 2/20 W/Turnaround & New
Crossing Pavements
18A. Lewis University Airport, Romeoville, Will County, Contract
No. LE032, Pave, Light & Mark Partial Parallel Taxiway System For
Runway 2/20
19A. Decatur Airport, Decatur, Macon County, Contract No. DE162,
Taxiway G From Taxiway G-3 To Runway 12/30, Incl. Taxiway G-3
20A. Decatur Airport, Decatur, Macon County, Contract No. DE262,
Taxiway G-4 From Sta. 150+00 To Sta. 325+00
21A. Decatur Airport, Decatur, Macon County, Contract No. DE362,
Taxiway G From Sta. 334+59.81 To Sta. 353+86.78
22A. Decatur Airport, Decatur, Macon County, Contract No. DE462,
Taxiway G From 319+00.05 To Sta. 334+59.81
23A. DeKalb-Taylor Municipal Airport, DeKalb, DeKalb County,
Contract No. DK148, Construction of a 2,225' X 100' Extension To
Runway End 20,
24A. DeKalb-Taylor Municipal Airport, DeKalb, DeKalb County,
Contract No. DK248, Construction of a 2,300' X 50' Extension To
Taxiway "C"
1LR. Menard County, Reclamation of Lincoln Coal Co. Mine Group,
The proposed reclamation project includes four abandoned mine sites
located in Menard County. The proposed work requires the removal of
concrete caps exploratory excavation (659 C.Y. Special Excavation)
of settled fill mate in previously filled shafts. The project also
provides for the shafts to be filled and resealed with a combination
of soil furnished by the contractor (406 C.Y. of Borrow Excavation)
and crushed limestone fill materials (1,3 tons). The project also
includes 0.8 acre of seeding, mulch, and soil.
###
|