Home
Project Overview
Summary of Improvements
-
Remove and replace the pavement on I-74 and I-155
-
Add a through traffic lane on both eastbound and westbound
I-74 to provide three lanes total in each direction of
travel
-
Reconfigure the I-74/I-155 interchange
-
Replace the bridges on I-74 over I-155 and Jackson St.
-
Remove the tunnels on Jefferson St. under I-74 and add
bridges
-
Remove the bridges over the abandoned railroad on I-74 and
build roadway in their place
-
Reconstruct on and off ramps at the I-74/Morton Ave.
interchange
-
Install traffic signals on Morton Ave. at the I-74/Morton
Ave. interchange
-
Construct median barrier wall on I-74 between the
eastbound and westbound lanes
-
Install highway lighting on I-74 and I-155
-
Install Intelligent Transportation Systems (ITS) elements
for traffic monitoring
-
Install drainage features
Objectives
-
Improve interchange and Interstate safety
-
Improve traffic flow
-
Improve deteriorating structures
-
Improve the I-74/I-155 interchange configuration and
efficiency
-
Improve capacity on I-74 and I-155
Construction Timeline
*All dates are weather dependent and subject to change. All
work will take place under staged construction. Please slow
down and use extreme caution while driving through the
project area.
2013 Construction Season (March – November)
-
Construction will begin on I-74 and I-155
-
Construction will begin on the ramps at the I-74/Morton
Ave. interchange
-
Construction will begin on Morton Ave. at the I-74/Morton
Ave. interchange
-
Temporary pavement will be constructed at the I-74/I155
interchange
-
Bridge construction will begin at Jefferson St., Jackson
St.
-
Bridge removal will begin at the abandoned railroad on
I-74
Winter Shutdown (December 2013 – February 2014) No work planned
2014 Construction Season (March – November)
-
Construction of the north ramps at the I-74/I-155
interchange
-
Construction of the I-155 bridges over I-74 at the
I-74/I-155 interchange
-
Construction will continue on the bridges at Jefferson St.
and Jackson St.
-
Construction will continue on the ramps at the I-74/Morton
Ave. interchange
-
Bridge removal will continue at the abandoned railroad
bridge on I-74
-
Construction will continue on I-74 and I-155
Winter Shutdown (December 2014 – February 2015) No work planned
2015 Construction Season (March – July)
-
Construction completed on I-74 and I-155
-
Construction completed on all bridges on I-74
-
Construction completed at the abandoned railroad on I-74
-
Construction completed on the ramps at the I-74/Morton
Ave. interchange
-
Construction completed on Morton Ave. at the I-74/Morton
Ave. interchange
-
Construction completed on highway lighting, ITS, traffic
signing, miscellaneous work items
|